Ginger will become bpTT’s fourth subsea development and will include four subsea wells and subsea trees tied back to bpTT’s existing Mahogany B platform. First gas from the project is expected in 2027 and will make up one of bp’s ten major projects expected to start up between 2025 and 2027. At peak, the development is expected to have the capacity to produce average gas production of 62 thousand barrels of oil equivalent per day.
Ginger is well underway with the first well completed!
Drilling will continue through 2026. We're also progressing with the fabrication of kit required for 2026 offshore topsides and subsea construction. Tubing hangers delivered to Trinidad & Tobago. These are critical to the production process. Preparation works have commenced on the Juniper platform for 2026 construction. Ginger flexibles will tie back to the Mahogany B platform and umbilicals to Juniper.